02-041-26 Workplan

Roland Alston · Roland Alston barn: 36x36 (1,296 SF) Builder's Basic horse b... · 4785 Hwy 166 · $178,694.87 fixed price

Cover

Job #
02-041-26
Title
Client
Roland Alston
Address
4785 Hwy 166, Douglasville GA 30134 (Chattahoochee Walk subdivision)
Contract sum
$178,694.87 fixed price
Cost basis
$151,436.33 (18% margin)
Target completion
TBD
BT Job
[BT job ID]

Site Access

Working hours
[NEEDS Trey: confirm any quiet hours]
Lockbox location
[NEEDS Trey]
Lockbox code
[NEEDS Trey]
Front door code
[NEEDS Trey]
Parking
[NEEDS Trey]
Daily protocol
Per signed contract. Owner provides site access. No HOA (Chattahoochee Walk is non-HOA).

Utility Shutoffs

Locate and photograph before any wall opens.

Electrical panel
[NEEDS Trey: location + 240V dryer circuit confirmed?]
Water main shutoff
[NEEDS Trey]
Hot water heater
[NEEDS Trey]
Gas shutoff
[NEEDS Trey]
HVAC
[NEEDS Trey]

Contacts

RoleNameReach
JCG OwnerAlex Johnsonalex@jcgbuild.com
JCG Field PMTreytrey@jcgbuild.com | (770) 291-4555
JCG OfficeAudrey McGrathaudrey@jcgbuild.com
ClientRoland Alston
Client inspector / maintenance[NEEDS Trey]

Emergency

ServiceNumber
Emergency911
Poison Control1-800-222-1222
Dig-safe811
Nearest ERLook up nearest ER based on job address before mobilization.
Power outageGeorgia Power 1-888-891-0938
Gas leakAtlanta Gas Light: 1-877-427-4321

Safety Plan

  1. PPE: safety glasses on all demo/cutting; hearing protection on power tools; dust mask N95 minimum on demo and floor prep.
  2. De-energize circuits at panel before any electrical work. Test with non-contact tester before touching. Lock-out tag at panel.
  3. Shut water at main before plumbing demo.
  4. Cover smoke and fire detectors during work; UNCOVER before leaving site each day.
  5. No open flame near gas cap until plumber confirms gas is capped at outlet.
  6. Concealed conditions (mold, rot, vermiculite): stop work, photo, notify Trey.
  7. Daily debris haul-off.
  8. Keep tools secured, doors closed when not on site.

Allowance Schedule

Owner allowances. Selections exceeding allowance trigger CO at cost+15% per JCG standard.

Item$ allowanceNotes
No allowances detected.

Sub Roster + POs

TradeSub$PO #Status
No subs awarded yet.

Schedule

Engine-generated Gantt + pay milestone view. Live source: 06 - Construction/02-041-26_Schedule.xlsx + .md. Update there to drive this workplan.
#MilestoneStartEndAmount
1Agreement Signing _(deposit)_2026-06-232026-06-23$35,738.97
2Clearing/Site Prep2026-06-242026-06-28$5,460.38
3Footing/Slab2026-06-292026-07-03$16,656.27
4Framing2026-07-042026-07-06$32,258.26
5Roofing2026-07-072026-07-11$9,765.68
6Housewrap/Windows/Doors2026-07-122026-07-16$7,829.35
7MEP Rough2026-07-172026-07-21$12,837.15
8Insulation2026-07-222026-07-26$945.07
9Siding2026-07-272026-07-31$10,521.74
10Drywall2026-08-012026-08-05$19,262.55
11Millwork2026-08-062026-08-10$252.02
12HVAC Trim2026-08-112026-08-15$2,703.94
13Electrical Trim2026-08-162026-08-20$5,591.64
14Plumbing Trim2026-08-212026-08-25$4,541.57
15Exterior Paint2026-08-262026-08-30$7,014.49
16Hardware2026-08-312026-09-04$168.00
17Final _(punch retainage included)_2026-09-052026-09-05$7,147.79

Trade Workplans (Per Sub)

Per-trade scope handoffs. Each sub gets only their scope; exclusions enforced.

No awarded subs.

Red Flags / CO Triggers

  1. COTrigger(category='Concealed conditions', description='Mold, rot, framing damage, water damage, or any other unforeseen condition discovered behind walls, under floors, or above ceilings during demolition or rough-in. STOP work + photograph + notify JCG PM in writing before proceeding.', source='standard')
  2. COTrigger(category='Owner scope change', description='Owner requests work beyond the signed contract scope (added fixtures, upgraded materials, additional rooms, etc). All owner-requested changes require a written CO with revised price and schedule impact before work begins.', source='standard')
  3. COTrigger(category='Material substitution', description='Specified material is unavailable, discontinued, or backordered with a lead time impact. Substitution requires written approval; price delta settles via CO.', source='standard')
  4. COTrigger(category='Code or inspection requirement', description='Inspector requires work not in original scope (e.g. additional GFCI, code upgrades on circuits being touched, plumbing venting changes). CO with the responsible trade sub at their unit rates.', source='standard')
  5. COTrigger(category='Schedule acceleration request', description='Owner requests completion before original target. Additional crew or overtime is a CO; original schedule remains baseline.', source='standard')
  6. COTrigger(category='Allowance overage', description='Owner selects a fixture / material / finish that costs more than the allowance in the proposal. Overage settles via CO on the next milestone draw. Allowance UNDER-spend is NOT credited.', source='standard')
  7. COTrigger(category='Permit fees exceeding allowance', description="Actual permit fees from the AHJ exceed the proposal's permit allowance. JCG documents actual fees + bills the delta cost-plus-15% per the proposal.", source='standard')
  8. COTrigger(category='Site conditions changed', description="Access blocked, utility shut-off issues, weather-driven delays beyond two consecutive days, or any condition outside JCG's control. Schedule extension + any delay-cost is a CO.", source='standard')
  9. COTrigger(category='Job-specific risk (from bid analysis)', description='2x6 T&G SYP stall wall pricing is a MED-LOW confidence market estimate ($7/SF installed, mid-low of the Atlanta-metro / Southeast SYP band $4-$10/SF). Estimator converts to a written sub PO before the wall-finish milestone begins; if the real bid varies, change order before work starts. Stipulated; not an open question.', source='job-specific (from Internal Cost Basis)')
  10. COTrigger(category='Job-specific risk (from bid analysis)', description="10' wall height at the eaves carries the validated framing dollar ($30,320 base + $400 stall RO add = $30,720). Estimator verifies workbook studs are 10 ft pre-construction; if 8 ft was assumed, ~$2,500-$3,500 change order at engineering. Stipulated; not an open question.", source='job-specific (from Internal Cost Basis)')
  11. COTrigger(category='Job-specific risk (from bid analysis)', description='Driveway is a HARD EXCLUSION + Owner-responsibility stipulation. Owner will scope and price the driveway separately when ready.', source='job-specific (from Internal Cost Basis)')
  12. COTrigger(category='Job-specific risk (from bid analysis)', description='Future Scope ballparks F-1 through F-4 (well, shared septic, service feeder, whole-property clearing) are NON-BINDING. They are NOT part of the contract sum. Hard numbers come via a separate commitment-letter exercise + site walk + sub quotes when the Owner is ready to commit.', source='job-specific (from Internal Cost Basis)')
  13. COTrigger(category='Job-specific risk (from bid analysis)', description='Category subtotals reconcile to $139,382 exactly (v2.4 P0). v2.8 pricing gate + v3.0 completeness gate + v2.9 package-aware archive verified this run.', source='job-specific (from Internal Cost Basis)')

Trey Field-Info Checklist

Fill the gaps marked above. Email each item to bt-data@jcgbuild.com with subject pattern:

UPDATE 02-041-26 <TAG>: <value>

Open the checklist form on phone

Attachments Index

  • Job Launch Packet: 06 - Construction/Pre-Con Meeting/02-041-26_Job_Launch_Packet.pdf
  • Schedule: 06 - Construction/02-041-26_Schedule.xlsx + .md
  • QC Checklist: 06 - Construction/QC/02-041-26_QC_Checklist.xlsx
  • Selections: 06 - Construction/Selections/02-041-26_Selections.xlsx
  • BT Setup Checklist: 06 - Construction/02-041-26_BT_Setup_Checklist.md
  • Permit Checklist: 05 - Plans & Permits/02-041-26_Permit_Checklist.pdf
  • Sub POs: 06 - Construction/Sub Contracts/
  • Ingest state: _ingested/job_ingest.json